How can I plan a product in IBP (using profit optimization SOP Operator) where the PDS uses two resources?

I have a product where the PDS has two operations, each running on a different resource. In the Production Resource master data, I have this PDS (one source ID) linked to two different production resources at the same location. When I run the Profit Optimization SOP Operator, I do not see production being planned on both resources. In fact, when I try to view the Capacity Consumed with regards to this material and location, only one of the two resources displays.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

avatar image
Former Member Dec 01, 2016 at 03:37 AM
0

hi Genva Anderson

on the source production you have to create this:

location production source id sourcetype

xxxxx yyyyy zzzzz P

xxxxx yyyy wwww P

then on the template production resource create this:

resourceid source id

aaaaa zzzzzz

bbbbb wwww

dont forget the modelation cost for each resource

. dont forget the imput kf too

i hope this can help you