Hi,

I have these 2 data sources 2LIS_03_BF and BX where it looks like there is daily delta and only 10 latest requests are kept in the PSA.

Now the requirement that came to me is to load the data from 21st July, 2016. I was not sure how I can go about it. If somebody can please put out the steps for me, it would really be helpful

TS

10 |10000 characters needed characters left characters exceeded

Hi TS,

If you want to have the older data then you need to have the set up Deleted and table filled and then extract the data using BUDAT.

To delete the set up table use (T-Code LBWG)

Fill the Setup tables using OLI*BW where * is the application

Regards

Vivek

0
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Las W Nov 29, 2016 at 12:08 AM
0

if the 2LIS_03_BF data source has BUDAT field enabled you can extract via this, BX has the BUDAT field but it has to be enable for selection. setup data deletion and updates has to be done as the initial steps in SPRO.

Please refer to online documentation on intiialisation as there are many.

Share
10 |10000 characters needed characters left characters exceeded
Raman Korrapati Dec 01, 2016 at 10:08 AM
0

Hi,

As already suggested, you can go with date filed for selection.

lets delete set up tables data at ecc side and fill it with possible selections which can covers data from 21.07.2016.

at info pack level, you can create repair full request and use selections on date field.

By using repair full request you can load missing delta data.

Thanks

Share