Former Member
Mar 23, 2010 at 10:02 AM

Multiple counter Plan

22 Views

Sir,

I have created cycle set using IP11Z

Package Nos. Cycl. Length Unit

1 500 Hours

2 1 Month

Created a Measuring Point for a Equipment,Have maintained annual estimate of 8760 running Hours.

Now my requirement is that the system should trigger order is such a way that if 1 Month is reached early it should create Maintenance Order or if running hours is reached earlier it should create order.

Now I have created Multiple counter Maintenance Plan using transaction IP43.

The task list assigned to Maintenance Plan has operations with maintenance Package of 1 Month.

Now when I schedule the maintenance Plan using IP10 I am not getting the desired output,am I following the right procedure or is there any thing wrong....

Please suggest

Nikhil Rai