HI Experts,

Requirement:

I have two versions: A01 for Legal consol and A02 for management consolidation.

Method Currency translation is different for both the versions. So i have created two methods CT1 for legal and CT2 for Management consol versions and also two tasks T03 and T04 for each method.

Issue:

Assigned the two tasks in the consolidation monitor hierarchy and now the two tasks are available in both the versions, which I dont want.

Ex: Version A01 required only T03 and in version A02 required only T04.

While assigning the tasks in the hierarchy, for Task T03, i have selected Version A01 and A02 for task T04, but still both tasks are available in the monitor.

Need your advice on how to set up this. I know it may be a simple, but I am not able to get the idea.

I am working on Version SEM 6.0 EHP3.

Regards,

Richard