Currently, users use IW39 to view maintenance work orders that are created automatically by the plant maintenance plan (they are of a specific order type). Is it possible to view the hours of work planned from the mtainenance plan itself? E.G A user could enter a future date range and the hours of planned work based on the time-based plan would appear.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Peter Atkin Nov 28, 2016 at 04:12 PM
0

Brandon,

This can be done via IP19 making sure you:

  • Select the "with task list" checkbox
  • Select the "with sub operations" checkbox
  • Select the "with further dates" checkbox
  • Select the "tabular" radio button

PeteA