can any body give to valuble solution my query is today i received 2000lts toluene means 8 drums out of 8 drums 4 drums is sled date 17032011 and another 4drums 17032012 can any body done this business process when i try usage decision tab only one time is possible any provision is there kindly guide me.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Mar 17, 2010 at 06:12 AM

    Hi,,

    Normally material like tolune comes in Batch managed .When coming material it should be in 2 batches which is having 2 different SLED ..

    When you do GRN of material with 2 line item say for 4 drums B NO-A & for *8 drums B No- B.

    After GRN system will create 2 lots for 2 batches & then take result fot 2 lots so that different SLD will get updated with 2 different SLED.

    But in your case you have done GRN with all QTY in with 1 line item their fore you are not abl;e to record SLEDs for the same.

    For any clarification revert me back.

    Regards

    SANIL

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 31, 2010 at 05:59 AM

    i am not get right answar