tolerance of the work order completion date.

239 Views

Hi Gurus,

I am trying to Technically close the work order and its giving me an error saying that the completion date is more than 30 days after the basic start date in the work order. The same happens if the date is more than 30 days before the basic start date.

Can any one tell me is there a way to widen this tolrance and some times the work order might get closed after the 60 days?

Regards