I have explode the BOM at schedule line with LUMF (TAP) and TAN.
Can any of my friend tell me the procedure how to control the target value ???
Means when I put 10 unit in the main item same will be duplicaated on the subitems level (10+10), i can manually change the sub item level, but the price is calculated on the 10 unit individually and header level shows the value of 20 unit.
Pls advise.
Regards
Issue resolved.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Imran
You can use ERLA or LUMF.
When you are using LUMF system assumes your total value of BOM is built up from individual items in BOM.
So if you want to use header level value use ERLA,and if you are using LUMF enter values at item level.
for individual pricing condition type u may use group condition routine when u are entering header level value and donot want accumulation.
Regards
Mandar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.