Hi,
I got a situation where in we are using CO11 for confirmation.
We have 3 Activities in the Std Values viz, Machine, Labour and Actual Weight
After entering the Yield Qty and pressing Actual Data, Machine and Labour are appearing, but Actual Weight is not Appearing.
Necessary settings in OPK4 and OPK0 are already in place.
Please guide.
Thanks in advance,
Harris
Dear,
There are 3 possibilities to populate the activity fields:
1) The system can propose them based on quantity, using the standard
formula, directly after entry of the operation being confirmed please check it in your order first
2) The system can propose them at the time of saving
3) They can be manually entered ~ however using this option, formula
will not recalculate using the settings from the Standard value key,
set for the work centre.
To set one of the above as default in customising, follow these steps:
- Call transaction OPK0
- Select the default Confirmation Profile
- Select the Default tab and set the default for Quants and Services
to 'Immediate Proposal' or 'Propose When Saving'
These options allow you to choose whether the activity proposal in
C011N is given immediately after entry of the operation to be
confirmed or upon saving the confirmation. However note that if
you subsequently override these proposals by maually entering activity
details, the formulae will not be recalculated and manually entered
data will take presidence.
Regards,
R.Brahmankar