Hi,

We are setting Efiling GB in our project .Please can you suggest how will the data flow in from SAP R/3 to XI.Do we have to use a file adapter to receive this data or the data will come in automatically into the XI system.

What are the settings that we have to do in R/3 and XI so that efiling data flows between the two systems.

Regards,

Shreshtha

Accepted Solutions (1)

Accepted Solutions (1)

prateek
Active Contributor
0 Kudos

Use client abap proxy to send data from R3 to PI. You need to enable Sproxy at R3. Search for "Activate abap proxy" on sdn.

Regards,

Prateek

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

While configuring HMRC E-Filing GB, we are facing errors on the ECC

system.Given below problem description.

1)No answer from the goverenment gateway received

2)An error occured while determining the Bussiness Systems

(sld_API_EXCEPTION)

Would you please let me know how to solve the issue and if you have any documents regarding HMRC, please send it to my mail Id it will be more appriciable.

Thanks & Regards,

Ravi.

Former Member
0 Kudos

I have just implemented and tested this on my project and are ready to go live with it.

check SAP Note 1400735 - End of Year Legal Changes 2009-10 which points you in the right direction of the e-Filing and SAP HR Content that you need for 2009/10 EOY.

also check these documents:

https://websmp110.sap-ag.de/~sapdownload/011000358700000286712009E/UserGuide.pdf

https://websmp110.sap-ag.de/~sapdownload/011000358700001114552007E/GenericXISetupguide.pdf

these guides are full and thorough

former_member189387
Active Contributor
0 Kudos

Hi Shreshtha ,

youe question is not clear

1. First you describe what you are going to act like data push from R/3 ie., are you going to use IDOC/BAPI/RFC etc.,,

data will come in automatically into the XI system.

Ans : Yes after you did the configuration from sender side and PI side

Regards.,

V.Rangarajan

Former Member
0 Kudos

Hi Rangarajan,

I wanted to know that when the user runs the report RPC35CG0 in R/3 and generates the XML ,then how will this data flow into XI.

There are some settings mentioned in the blog

Do I have to ask the Basis guys to do these in the R/3 server.Apart from the settings mentioned in this blog,do we have to create anything in XI.

Regards,

Shreshtha

santhosh_kumarv
Active Contributor
0 Kudos

>>Apart from the settings mentioned in this blog,do we have to create anything in XI.

check this....

[E-Filing GB Configuration|http://www.sdn.sap.com/irj/scn/weblogs?blog=/pub/wlg/13616] [original link is broken];

~SaNv...

prateek
Active Contributor
0 Kudos

Do I have to ask the Basis guys to do these in the R/3 server.

Yes.

Regards,

Prateek

Former Member
0 Kudos

Hi Experts,

All the configuration and design is done but while testing the scenario. It's giving an error mapping error. When I checked the configuration under Interface Determination, it's saying the interface is not present in the business system. So, i checked in SLD and installed the software component in business system. Then how to refresh in Integration Directory.Because still in Business system I am unable to find the interfaces of that particular software component.

Please advice.

Regards,

Nutan

Former Member
0 Kudos

Hi,

Please make sure PI administrator has imported required content for BASIS and HR in Integration Repositry.

Regards,

Shehryar

Former Member
0 Kudos

Hi,

Those Components are already present in IR. I feel as if my business system is not getting updated so, unable to find the interface

Regards,

Nutan

Former Member
0 Kudos

Have you tried refreshing the SLD cache on ID?

Former Member
0 Kudos

Hi,

Ya, I have tried sld cache refresh and sxi_cache.

When I am testing the scenario then getting mapping error.And when I tried to take the payload in IR and test in mapping its giving error as:

The source or target structure has been changed or could not be found in the Integration Repository. The mapping definition contains elements or attributes that do not exist in the changed structure. The relevant entries will be deleted

Target structure has no such path: /ns0:GovTalkMessage/ns0:Body/ns3:IRenvelope/ns3:EndOfYearReturn/ns3:P35/ns3:Summary/ns3:PAYE/@ns3:SubcontractorTax. Skipping mapping

for all the fields it is showing like this.

How can I resolve it. Whether I should reimport the E-filing software component.

Regards,

Nutan

Former Member
0 Kudos

Hi,

1. Make sure the version of E-filing package in PI IR and SAP backend HR SP level are compliant. Sometimes, old content is loaded in PI or the HRSP level is not up-to-date. Since HMRC's namespace changes every year to reflect the current tax year, you run into namespace issues.

2. Are you sending data from a non-prod or a prod system?

Regards

Former Member
0 Kudos

Nutan

there are two lots of Content to Import into PI. e-Filing and SAP HR. the e-Filing (version 17) is for the HMRC side and the SAP HR (version 53)is for the SAP side.