Dear,

I have a production order with 2 operation, the first one is related to hours consumption and needs to be confirmed by a dept, the reference routing is set up with a control key that does not do the automatic good receipt.

the second operation is the automatic good receipt (mvt 101).

Now what I am not able to do and I belive that you can help me is that you can not confirm operation 2 since operation 1 is completely confirmed and delivered.

I set up in OPK4 the following information:

Operation sequence - Error when operation sequence is not adhered to

Underdelivery - is not checked

Overdelivery - is checked

Results Rec. (QM) -

Now with the parameter I set up I belive that SAP does not allow me to confirm operation 2 till operation 1 is completely confirmed.

If I provide to partially confirm OP 1 then I am able to confirm fianlly operation 2.

How can I avoid it?

Are my setting ok?

Many thanks for your support