on 03-11-2010 2:22 PM
hi,
plant - for trading material
can we get direct PR from MRP run (only PR not PO) if post dated SO booked for the material
if yes tell me how.
Hi
Yes you can create PR from MRP. But for trading even ITEM category(customer ind.requirement) in SO can also create PR with out MRP. I mean when SO is saved PR willl be generated. Check item category config in t.code Vov7. and vov5 and Vov6 for schedule line of SO.
Regards
Antony