Error Message: Number is not in external Interval (Testing Schedule)

Former Member
0 Kudos

Hii ,

Iam working on Stability study process. I have maintained stabity test with materiial (QS) & performed my test upto Initial test of Inspection lot. But when i click create Testing Scheudle in the Notification (QM02) , system asks for testing schedule data for

Maintenane strategy, scheduling period.

On clciking create testing schedule , system throws error message "Number is not in external interval". I have maintained all the prerequite setting on number range in following spro path stability study>testing schedule for stability study> Category--> no range.

For Group ST 600000000- 6999999999 for Intenal & 70000000-7999999999 for external. But still iam facing with error message ""Number is not in external interval". It throws message no "IP324" . Even I had cross checked with maintenance setting, but error message remains . How to resolve this issue?

with regards,

K.Lokesh.

Edited by: Lokesh K on Mar 11, 2010 1:13 PM

Edited by: Lokesh K on Mar 12, 2010 5:55 AM

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Hi Lokesh,

did you actually enter a number ( i.e. 70000001)?

Usually Stability studies are created using the external number range so that ringing names can be used for the studies:

Example:

Material: 000000000000000001 acetylsalicylic acid

Stability study: ASA1

I hope that this information proves usefull.

Regards

Isabelle