PO not found during Confirmation in ECS scenario

28 Views

Hello Experts,

We are in the phase of implementing ECS scenario in SRM 7.0 and one problem we are facing during implementation is :

When PO is created with refernce to shopping cart in SRM system and we have done some changes in PO and

now user is not able to find the PO for confirmation and during analysis i found

there are

2 links to this purchase order for the shopping cart.

In bbp_pd for the SC we will see that under the Header and Item links there are 2 lines. Both links point to

the same purchase order. The difference between them is that one link is for the changed version of the PO and another - for the active.

This is wrong. Normally we should have only one link to the PO.

Because of 2 links existence purchase order is not found."

Please suggest the solution. we have already implemented Sap note "1423139 ".

Thanks!!

Sunny Sharma