on 03-11-2010 6:12 AM
Dear Experts ,
IN Ecc sales and operation planning we have a functionality , when sales order is executed , Demand is automatically consumed
How to manage the same scenario in Demand planning in APO , and what are the key configuration
Please advise
Regards & Thanks
Raj
Hi,
I recently worked with a client for the same requirement.
Requirement Strategy 20 (In APO)works very well ,i.e PIR's or Forecast gets consumed my incoming sales order.