on 03-11-2010 2:49 AM
Dear All,
When we start cost planning report (S_ALR_87013547),why output of that report from the WBS level, besides cost planning only at the level of activity? Can anyone help?
Regards,
MamaRara
Hi,
Please attend SAP PS course then you can understand the various functionalities of SAP.
Regards,
Muzamil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Your question is very vague.
In the selection screen enter network number if you do not want to see WBS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Virendra Pal,
I mean in the report should not appear cost planning at WBS level, because we did not make planning at that level, but we just make cost planning activity level. And the value stated in the WBS level to the total confusion of the cost planning, as part aggregated. Did you ever find an error like this? Is there a process conducted outside the procedures?
Regards,
MamaRara
User | Count |
---|---|
100 | |
8 | |
8 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.