MPS configuration or setting master data of final product.

224 Views

Hello.

I have following problem to solve.

1. In Demand Management (transaction MD62) I have set planned independent requirements in every month

up to the end of 2010 year.

2. Now when I run MPS total plannig (transaction MD40 or MDBS) I got planned orders in every month up to the end of 2010

year. The volume of planned orders in every month is equal to volume of planned independent requirements in every month.

3. End user expectation is that volume of planned orders in next month is the sum of volume planned independent requirements

from the next two months.

How to solve this problem?

Should I configure MPS or change masted data for FERT or both?

Best regards

Bogdan