Costplanning

Former Member
0 Kudos

Hi,

What are the pre req of costplanning

Regards

Accepted Solutions (1)

Accepted Solutions (1)

nitin_patoliya
Active Contributor
0 Kudos

That is based on which cost object you are doing cost planning & which planning method you are using. Request you to refer cost planing section of online help.

Some most basic setting are as below.

For WBS : planning indicator should be ticked. Planning profile maintained properly

For Network Activity : Control key should have ticked cost relevant indicator, Planning profile etc, work center in activity properly defined ( i.e. KP26 ) etc .

With Regards

Nitin P.

Former Member
0 Kudos

hi,

can you tell me regarding control key

where i have to check cost relevant indicator

Former Member
0 Kudos

Hi,

As nitin said:

Check in OPSB for planning indicator

Control key :OPSU.

Havea look on SAP help.

Regards

Guruprasad

Edited by: Virendra Pal on Mar 10, 2010 9:17 AM