Skip to Content
0
Former Member
Mar 08, 2010 at 08:30 PM

Customizing error for work schedule

34 Views

Hi All,

I created a new WS rule effective 01.02.2010 but I received a Customizing error for work schedule when I try to create an absence or run pt60. Then I changed the effective date to 01.12.2009 and the error is vanished.

I checked help and found that "If you want to create a work schedule from January through December of a particular year, you must include December of the previous year and January of the following year". But if I change the effective date to 01.12.2009, in IT0007 the user can use the new WS rule from the same date.

Is there a way that we make the new WS rule available as on 01.02.2010 in IT0007?

Regards

Naveen