Dear All,

I am in the process of activating the engineering change management for BOM and Routing.

I did the necessary setting to work ECM.

Now my problem is we have different plants and the ECM has to be activated only for 2 plants.

To make change number mandatory in CA01 and CA02 for these 2 plants. i followed the below steps.

IN T CODE OP5A- PP TASK LIST INITIAL SCREEN - CHANGE NUMBER - CHOOSE RADIO BUTTON INPUT - SELECT INFLUENCING -SELECT PLANT -CHANGE NUMBER - ENTER PLANT - CHOOSE RADIO BUTTON REQUIRED

Same like that I did for both plants. Even after this setting it is not allowing without change number.

Can any one help me to solve this issue.?

Thanks in advance

Ganesh

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

I am not clear with your requirement.

Do you want ECM mandatory for only 2 plants and rest of the plant it is not mandtory, is this what u want??

Edited by: Sarvan on Mar 8, 2010 3:57 PM

former_member205362
Active Participant
0 Kudos

Yes.

Former Member
0 Kudos

the setting in the field selection parameter should have helped you. but i dont know why i didnt work. also check with your SAP security team whether they can

control using authorisation ( C_AENR_BGR , C_AENR_ERW)

Regards

former_member205362
Active Participant
0 Kudos

Thanks for your reply.

After giving authorizations also problem pertains the same.

Can any one tell steps followed in field selection parameters is right or wrong?

Regards,

Ganesh

former_member205362
Active Participant
0 Kudos

Can any one please reply.

Regards,

Ganesh

former_member205362
Active Participant
0 Kudos

I followed transaction variant(SHD0) to solve my issue.

Regards,