cancel
Showing results for 
Search instead for 
Did you mean: 

Project Progress

Former Member
0 Kudos

Dear All,

In continuation to earlier question, requirement is to get progress from Project system.

What measurement method we shopuld suggest?

Regards,

Samba

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

You can use Progress report CNE5 , for data to be populated in CNE5 , you will have to run CNE1.

for both these reports populate the progres method at the WBS/ACTIVITY level.

You may use CNPAWB (progress analysis workbench) to monitor the progress.

Regards,

Anshvinder

virendra_pal
Active Contributor
0 Kudos

Forecast workbench is only available in ECC6.0 enhancement pack 3+ (could be 4 just check)

former_member203108
Active Contributor
0 Kudos

You can check this link

Edited by: Virendra Pal on Mar 4, 2010 10:46 AM

Link removed

Former Member
0 Kudos

Thanks for the link..

But I am not able to understand how/ what reports will be drawn for progress.

1.0 I have done automatic scheduling of Activities.

2.0 Actual dates from Activity are extrapolated to WBS Basic dates.

Now user wants report for progress.

Regards,

virendra_pal
Active Contributor
0 Kudos

You need to first understand what the user means by progress, then search for the suitable functionality map in SAP PS which could be obtained from standard reporting or using Project Progress functionality

Former Member
0 Kudos

Hi Virendra,

The requirement is they want to get Planned Vs Actual in terms of time. ( not cost).

They will input duration/relationssships on Activities. Scheduling will be carried out.

The activity confirmation will be done.

We had suggested Estimation Method but they want progress from SAP activities.

Regards,

virendra_pal
Active Contributor
0 Kudos

Why don't you use the CN47N report

When doing confirmation if you enter the forecast dates to complete and the estimated work left then you will get a good picture of the progress based on time