Dear All,
In continuation to earlier question, requirement is to get progress from Project system.
What measurement method we shopuld suggest?
Regards,
Samba
You can use Progress report CNE5 , for data to be populated in CNE5 , you will have to run CNE1.
for both these reports populate the progres method at the WBS/ACTIVITY level.
You may use CNPAWB (progress analysis workbench) to monitor the progress.
Regards,
Anshvinder
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can check this link
Edited by: Virendra Pal on Mar 4, 2010 10:46 AM
Link removed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Virendra,
The requirement is they want to get Planned Vs Actual in terms of time. ( not cost).
They will input duration/relationssships on Activities. Scheduling will be carried out.
The activity confirmation will be done.
We had suggested Estimation Method but they want progress from SAP activities.
Regards,