I have a problem concerning user status and budget status.

My client wants to not allow the release of the project if the budget has not been approved. I tried to use the user statuses using a status called AVA2, which should be activated (automatically) when system status changes to AVAC. From what I saw there is no business transaction that allows you to set the user status when the budget is released.

The main purpose is to prevent the release of the project if it has not been budgeted

Best regards,