Skip to Content
0
Former Member
Mar 03, 2010 at 06:16 AM

Un-Production - Can you perform prod confs for negative quantities?

14 Views

Ok so I don't have a system I can use at the moment to set up a scenario and test so I thought I would write a question on here.

Does anyone know if it is possible to do a "negative" production confirmation, the end result being a 102 of the finished good and a 262 of the component materials?

I have an example where a production order was used to produce an item some time ago. I want to debundle the components so I can sell them separately and I was thinking about using a production order for the process. I know I could do some kind of inventory adjustment but I want to use the prod ord to collect costs (including perhaps some activity costs like labor, etc.)

Has anyone done this before?

Mark