Hi,
After running MRP, we found that the system generates schedules for the line items blocked in the scheduling agreement.
In this case, the source list is valid and I have not blocked the source list and MRP 2 indicator has been maintained.
However, instead of block, if I mark for the delete the schedule agreement line numbers, it generates PR and similarly when I remove the MRP indicator 2 from the source list, it generates PR.
Earlier when Scheduling agreements were blocked, then also it used to generate PRs only and it never raised schedule lines.
We have recently applied support pack level 32 for SAP 4.7. Is it because of this.
Regards
Shankar