Dear all

Can we exclude storage Location from MRP from planning. and can we restrict the shipping of that goods if stock is at that particulor storage location even though stock is in unrestricted use

Regards

Pravin

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Pravin,

A common way to exclude material from BOTH MRP planning AND shipping is to move the material to Blocked Stock.

Rgds,

DB49

Answers (3)

Answers (3)

Former Member
0 Kudos

hi

thanks for reply but how to restrict for shipping?

REgards

pravin

Anupam1143
Active Contributor
0 Kudos

HI

You can check the same by moving the material to blocked stock and in OPPQ under the Available stock deselect the

Blocked stock check box.

I hope it will works for u

Regards

Anupam Sharma

Former Member
0 Kudos

Dear Pravin,

1) At material level, you can go to MRP - 4 view & maintain value as 1 for storage location

2) At plant level go to OMIR t-code and maintain value as1 for required storage location

3) then Run MRP, system will not consider the stock for that particular storage location

Regards

Madhu Kumar

Anupam1143
Active Contributor
0 Kudos

HI

You can exlude the storage location from MRP run using t code MMSC for the material and MRP indicator 1 and t code OMIR for that storage location in SPRO

Check and revert

Regards

Anupam Sharma