on 03-02-2010 8:40 AM
Dear all
Can we exclude storage Location from MRP from planning. and can we restrict the shipping of that goods if stock is at that particulor storage location even though stock is in unrestricted use
Regards
Pravin
Pravin,
A common way to exclude material from BOTH MRP planning AND shipping is to move the material to Blocked Stock.
Rgds,
DB49
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
thanks for reply but how to restrict for shipping?
REgards
pravin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Pravin,
1) At material level, you can go to MRP - 4 view & maintain value as 1 for storage location
2) At plant level go to OMIR t-code and maintain value as1 for required storage location
3) then Run MRP, system will not consider the stock for that particular storage location
Regards
Madhu Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI
You can exlude the storage location from MRP run using t code MMSC for the material and MRP indicator 1 and t code OMIR for that storage location in SPRO
Check and revert
Regards
Anupam Sharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.