Dear Experts,
We have created a Factory Calendar as only First Saturday as Working Days.
We have created a Contract for 1 Year with Cycle/Unit as 1 DAY
Scheduling Indicator - Time - Factory Calendar.
When we schedule the Plan, it shows only 11 calls instead of 12 calls.
Can any one help me why the First Call is missing.
Regards,
Shareeq
Hi Ahamed,
Check the entry given in last maintenance completion date while carrying out Scheduling.
If you give today's date there, then only 11 calls will be there. If you give a date which is one month ago, then you will get 12 calls starting from today's date.
MLN Prasad
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Contract Start Date : 10.03.2010 , Contract End Date : 09.03.2011.
Scheduling Day is Today and Cycle start date is also today but it is creating only 11 Calls. Calendar - Only First Saturday Working Day.
The Dates are 01.05.2010
05.06.2010
03.07.2010
07.08.2010
04.09.2010
02.10.2010
06.11.2010
04.12.2010
01.01.2011
05.02.2011
05.03.2011
It has to create for 03.04.2010 but it is not creating. Please post your thoughts
Regards,
Shareeq
Hi Shareeq,
Your problem is in Maintenance Plan >>> Scheduling parameter >>> Scheduling indicator >>> Field >>> " Factory calender"
This Field "Factory Calender" implies = Next Working day + Cycle/Unit as 1 DAY
You are scheduling on 10.03.2010 so due to this your fist call will be = 03.04.2010(which your next working day) + 1day i.e . 01.05.2010.
When you select date 10.02.2010 your first call will be will be = 06.03.10(which your next working day) + 1day i.e 03.04.2010.
Hi Talankis,
Got it from net.
please reffer below link.
http://help.sap.com/saphelp_erp60_sp/helpdata/EN/3c/abb36a413911d1893d0000e8323c4f/content.htm
Hi Shareeq,
Just to clarify regarding scheduling by Factory calendar.
System Schedules the plan (strategy:Factory calendar) from working day of factory calendar. (this conclusion I am making after simulating number of scenarios. Pls correct if it is wrong)
In the case mentioned by you since the scheduling is done on 10.03.2010, next working day as per calendar is 03.04.2010, scheduling is done from 03.04.2010 even though you have entered 10.03.2010 and first call is generated on 01.05.2010.
If you schedule from say 03.04.2010 , which is a working day as per your calendar, scheduling is done from 03.04.2010 and first call gets generated on 01.05.2010.
Hope this clarifies std SAP behaviour.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Please check the offset , set it accordingly then you should able to get the what sequence you want.
regards
krishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.