Hi all

I am working with PPM and alternative modes.

But I have problems to balance orders into different modes.The systems always takes the priority mode. So one all the orders are planned in the same resource althought others reources have enought capacity.

Is there any heuristics to balance orders into resources taking based on available capacity??

Thanks!!!

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Fernando,

you can check for the REM heuristics for multi resource planning (even). You can use its template to design your own algorithm as well for your business requiremets.

Refer to below link for SAP support on heuristics and setting procedure.

http://help.sap.com/saphelp_scm41/helpdata/en/0c/7f7304363611d4b5bb0004ac160649/frameset.htm

Let me know if it helps

Regards