Cutover - components update

Former Member
0 Kudos

Hello ALL

Our client upgrading from 4.7 to ECC 6.0 - Now all the project structure we have to migrate from 4.7 to ECC6.0.

(Project definition, wbs elements, network, activities, components)

now there are open PR's witn noumber 1234 in 4.7 for the components attached in the project.

I am trying to upload the components to ECC 6.0 using BAPI "BAPI_NETWORK_COMP_ADD" will it generate the PR swith same number 1234 as in the old system 4.7.

will this be possible?

any one suggest how we can take the open PR to new sap system.

Thanks for all in advance ,

Thanks,

Srihari.G

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Not quite sure why you would want to use back the same PR number, any compelling business need for this?

If there is no justifable reason, then better to allow system to generate a new number.

But if you want it to be the same as per legacy system, then inform your MM consultant to define an external number range as per your need & then assign the same to the document type. This way you can use back the same PR numbers.

Regards,

Vivek

Former Member
0 Kudos

Hello Vivek

In that case we need not have to assign Components to projects itself for the open PR's. is that a correct statment.

Thanks,

Srihari.G

Former Member
0 Kudos

Hi,

Just to be clear PR - Purchase Requsition.

So now if you do not assign the components to the network - activity, how do you intend to drive demand for these components?

Regards,

Vivek

virendra_pal
Active Contributor
0 Kudos

you could create a seperate document type for preq

set that in material configuration for network set document type

set the number range as external - prefix an E and 1234(old number)

after cutover change configuration to set the document type to the corect one with internal numbering