on 12-17-2018 6:35 AM
we make PIR in Plant A.
MRP make STR in Plant A for procurement from Plant B(manufacturing Plant).
When finishing manufacturing, Stock transfer to Plant A and then good-issue for sales in Plant A.
But Sometimes, Good issue plant used to be changed from Plant A to Plant B,
because Plant b is more close to customer.
in this case, good-issue in Plant B can reduce PIR in Plant A?
BADI? Exit?
Hello
The options to reduce PIRs in another plant are using a stock transfer or planning with a planning material. See detrails in SAP Help below:
There is a BAdI to influence PIR reduction (MD_PIR_FLEX_CONS) but it cannot be used to force the reduction of a PIR which wouldn't be reduced according to the standard settings.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.