Dear all

Could you please let me know how to handle ROC_Out to flow only for confirmed schedule line items and not for the changes (like delivery date,price change and other details that has been carried out in PO in SNC

Regards

shailesh

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Johnny Li
Dec 13, 2016 at 08:56 AM
0

Hi Shailesh,

Unfortunately there is no such functionality available in SNC, publishing the purchase order sends the complete order in the XML as per design and not just the recently confirmed lines. In the PO process, SNC uses the so called "full transmission", which means that all the items and components are sent in every related case.

Best regards,

Johnny