Hi Gurus,

I am getting problem during costing of cost network activity.

I planned 10000 usd on the cost network activity but when I run the report it only shows 77%(10000) of the total plan cost and overheads.

Can anyone tell me why this is happening or Do I need to make any configuration changes.