Skip to Content
avatar image
Former Member

Network Activity Costing

Hi Gurus,

I am getting problem during costing of cost network activity.

I planned 10000 usd on the cost network activity but when I run the report it only shows 77%(10000) of the total plan cost and overheads.

Can anyone tell me why this is happening or Do I need to make any configuration changes.

Thank You

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Feb 26, 2010 at 04:29 AM

    Check with removing costing sheet. from Network activity and other objects.

    With Regards

    Nitin P.

    Add comment
    10|10000 characters needed characters exceeded