Hello all,

I unable to delete CustSt requirement from MD04 for assembly material. Can you please anyone advice is there anyway clean-up the old CustSt requirement from MD04.

I have tried below options but doesn't work

1. Set Technicially completed for the corresponding orders

2. Run MD02 with Delete and recreate planning data option

3. Try to block the sales order but that field is grayed out

Thanks,

Raj

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

4 Answers

Phanikumar Valiveti Nov 28, 2016 at 05:29 AM
0

Firstly we should run Program SDRQCR21 in correcting the requirements.Pl confirm.

But I got some doubts-can you please clarify.

On 1. How you have completed Techo in this case-Have you already processed these requirements upto Planning/Production orders & get it released.

On 2. If Techo done-why delete options used with MD02?

On 3. Why sales order block instead of rejection?(Some blocked orders enable further process of requirements update based on config)

Phanikumar

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Nov 28, 2016 at 10:31 PM
0

Thank for the response, I have executed this program SDRQCR21 but it doesn't work.

Please find my response below

On 1. How you have completed Techo in this case-Have you already processed these requirements upto Planning/Production orders & get it released. – Yes. It already processed. The requirement is for assembly material process. In this case production order will automatically create with the reference of sales order and item. But stay in the MD04 as a open sales order

On 2. If Techo done-why delete options used with MD02? – This one is not related to Techo, However I have just tried to fix for other CustSt requirement in MD04.

On 3. Why sales order block instead of rejection?(Some blocked orders enable further process of requirements update based on config) – Since sales order is linked with production order, system doesn’t allow to do reason for rejection or delete the item.

Best regards,

Raj

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Dec 01, 2016 at 11:19 PM
0

Hello all,

I unable to clear CustSt requirement in MD04 for Assembly material. Since sales order is linked with production order, system doesn’t allow to do reason for rejection or delete the item. Can you please advise?

Thanks in Advance,

Raj

Share
10 |10000 characters needed characters left characters exceeded
RAJA SEKHARA REDDY BANNURU Feb 15, 2017 at 10:58 AM
0

Hi

Please try with the below steps :

Step1 : Set the Sales Order with the Reason for the Rejection : (Ex : Cancellation required by the Customer)

As shown below

Step

Step 2 : Look at the MD04 ( You will still finds the Production Order & Sales Order Ref)

Step 3 : Set the corresponding Production Order to Technically Complete

Step4 : Now Look at the Stocks & Requirements List : MD04

Sales Order is completely removed automatically from MD04 ( As shown below)

Try with this steps & kindly revert back with your back, if you are still facing the Problem

Thanks & Regards : Raja Sekhara Reddy B


0i2h1.png (43.3 kB)
enzfq.png (33.0 kB)
bzuwx.png (31.2 kB)
favgj.png (26.1 kB)
Show 1 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Hi,

Nice explanation and screenshots. Thanks for the effort. As you suggested I can manage to delete the item and do technically completed if item is open for delivery. But system doesn't allow us to change it to Reason for rejection for partial delivered items and production order has already been created with full quantity. Is there any way delete partial completed item that is showing in MD04?

Thanks & Regards,

Raj