Copy key figure values in the past period - Using macro job

59 Views

Hi Guys,

As per the dataview config past period is blocked for input (Jan 2009 to Jan 2010). I am trying to copy one keyfigure value to another in the past period using the macro. When I run the macro in the planning book it showing the copied values in the target keyfigure. However If I ran the same through background job copied values not saved in the target key figure.

I know It is possible to copy the key figure using the /SAPAPO/TSCOPY Transaction.

Questions:

By using macro job, Is it not possible to copy the values in the non-editable keyfigure (like past periods blocked for input).

If possible, what is the process to copy the values (without making the past period allowed for input).