Hi Gurus,
Need your expert advice on one of our issues.
We have a requirement that AMC should be taken for the past 6 months regardless if there is any usage or not. Standard behaviour is that during MRP Forecasting run, zero values in the earlier historical values are not taken into account.
For instance forecast period is set to '6' however, only last period has a value of 19.17 and others are zero in the historical data.
When we execute the forecast run system actually considers as 1 month even if we defined 6 month.
If standard SAP doesn't cater for the above, is there a way to twig the system to achieve the above objective? If yes, how can this address the zero usage and can it be restricted for a specific group of users?
Thanks.
J&J