Hi all,

Is it possible to update Fixed Asset Master Data, SAP B1 version 9.2.? I would like to change quantities.

Thanks in advance!

former_member588507
Participant
0 Kudos

Hi Markovic,

Can you tell me which way you are importing the Fixed asset it is DTW or SAP Import feature?

Regards,

Satish

0 Kudos

Hi Satish,

I have imported fixed assets master data via import fixed assets master data from Microsoft Excel. Please, could you tell me what is the procedure to update quantities of fixed assets which are already imported in SAP b1.

Thank you very much!

Accepted Solutions (0)

Answers (5)

Answers (5)

0 Kudos

I tried to update fixed assets quantities from excel ,as you have told me, in sap b1 but the problem is “code is missing-items-row number 0; define a code”.Can you tell me please how to import fixed assets quantities in sap b1 step by step?

Abdul
Active Contributor
0 Kudos

You can update quantity before posting any transaction...or add a column of quantity in your template and remove all other columns except asset code and try DTW to update records.

0 Kudos
I have tried to update fixed assets quantities from excel ,as you have told me, in sap b1 but the problem is “code is missing-items-row number 0; define a code”.Can you tell me please how to import fixed assets quantities in sap b1 step by step?
former_member588507
Participant
0 Kudos

Hi Markoic,

I have uploaded FA item with quantity but its not taking quantity so I think you does not need to update the quantity.

Quantity matter in capitalization of fixed asset so you have to upload quantity at the time of capitalization and go back and check in FA Item master it will reflect.

Regards,

Satish Gupta

0 Kudos

Thank you, I know that but, is it possible to update fixed assets master data by quantities via text file which you have mentuoned before and how to do that?

0 Kudos

Hi Gupta,

Thanks for the answer, but I have just imported fixed assets master data without quantities and there is no any other transaction. For example, depreciation, retirement etc. Can I update quantities via import fixed assets form excel in SAP b1?

Kind regards

former_member588507
Participant
0 Kudos

Hi markovic,

You can update master data by using DTW as Mannan said but you cant update quantity as a master data, Quantity required at the time of capitalization of FA.

So you don't have to update quantity, If you want to update any other master data you can.

Regards,

Satish

former_member588507
Participant
0 Kudos

Hi jasmina,

You can not change quantities if transactional document once added.

Regards,

Satish Kumar

0 Kudos

Hi Gupta,

Thanks for the answer, but I have just imported fixed assets master data without quantities and there is no any other transaction. For example, depreciation, retirement etc. Can I update quantities via import fixed assets form excel in SAP b1?