reschedule does not update the schedule line

Dear All expert,

After upgrade to ECC6.0, the reschedule does update the schedule lines eventhough it list all the required to be update in the list.

As I checked , it update the ekpo successfully but does not update the eket.

Is there any suggestion ?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Feb 24, 2010 at 05:58 AM

    Hi,

    On the initial screen of V_V2

    Remove tickmark of SIMULATION, Then it will update schedule lines in sales document