Producing up to a certain level every day

ngiannopoulos
Participant
0 Kudos

Dear all,

I have the following question: i have a material that can be produced at a maximum of 10.000 pieces a day. No matter how many requirements i have, my roof is this 10.000 pieces.Now, there are days i have more requirements than 10.000, there are days i have requirements less than 10.000, and at the end, i have days with no requirement at all. In the days i have no requirement at all, i need to produce these 10.000 so i make stock which i need latter. Therefore, in these days i have to introduce a VSF requirement of 10.000 (or so)

Is there any way of combining all these, so i end up to a feasible plan, so as in the days i have a requirement i produce only the difference or if the requirement is bigger of the 10,000 to somehow split? Or, in the days i have a requirement, the VSF requirement is not included?

I have been thinking of using a manufacturing table or a simple SOP form... But any suggestions are welcomed.

Best personal regards

Nikos

Accepted Solutions (0)

Answers (2)

Answers (2)

ngiannopoulos
Participant
0 Kudos

Ηello all,

problem was solved using VSFB requirements type

ajay_bakshi
Explorer
0 Kudos

HI Nikos Giannopoulos

Have you tried forecast based Planning

Kindly go this tread i think it will help you .

Forecast Based Planning – Yearly Consumption and Single PR for Forecasted Values