Former Member
Feb 23, 2010 at 09:37 AM

Overlapping of time at different material level

23 Views

Hello Friends,

My requirement is bit different. Suppose i have four levels of material i.e FG, SFG1, SFG2, RM.

Now here there current practice is suppose if they have to produce FG of 15 qty, than first they manufacture SFG2 on first machine. As soon as first piece of SFG2 is produced on first machine, it gets transfered to another machine for producing another sfg level i.e SFG1.Likewise as soon as first piece of SFG1 is produced on second machine, it gets transfered to another machine for producing another level i.e FG.

Now problem is through mrp they want scheduling like this. Is it possible to achieve such type of scheduling through mrp (lead time scheduling or basic date scheduling).

Please share your valuable input.

Note: I suggested them to club this operations into one level only and do the overlapping but they dont want like this. For each operation they want to maintain differnt level.