Wrong dates in MD04

eweolsze
Discoverer
0 Kudos

Hi,

we have a problem with dates in MD04.

GR date is the same as basic finish date instead of scheduled finish date. In the past it was ok (GR date in MD04 was the same as scheduled finish date) but now it doesn't work.

Why is that and how to change it?

MD04 shows this date (in the red circle)

instead of:

Prasath
Contributor
0 Kudos

Hello,

Your Post is not clear.Please post much more details with screenshots.It would be better for to understading.

Regards,

Prasath

eweolsze
Discoverer
0 Kudos

I'm sorry - I've pasted screenshots but somehow they are not visible.

Please check the attached file. I hope now it is clear.

ps.png

Accepted Solutions (0)

Answers (2)

Answers (2)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

In your planned order routing, go to the sequence and change the alignment key.

Regards,
Caetano

Prasath
Contributor
0 Kudos

Hello E T,

Planned order basic finish date is calculated by in house production routing date..Production date or scheduled date are depends on OPU3 and OPU5 customization setting .Please provide the detailed scheduling tab.

Regards,

Prasath E

eweolsze
Discoverer
0 Kudos

Hi,

thank you for your answer. Please check the attachment

ps2.png

- I hope this is what you've asked for.

I know that basic dates and production/scheduled dates are calculated in differents ways. They can be the same but not always. Honestly we don't need and don't use basic dates. The most important for us is scheduled finish date (or production finish date). And it used to be displayed in MD04 as Goods Receipt date.

Regards,

ET