how to find PO from Material document in external subcontracting

Hi,

I create a subcontracting PO with main item line and components.

and sends the items to the external vendor by doing a transfer posting (mb1b) with movement type 541.

having that transfer posting document number only, is there a way to get back to the corresponding PO document?????

(keep in mind still i hvnt done the GR, the materials are with the vendor)

Cheers

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

5 Answers

  • avatar image
    Former Member
    Feb 18, 2010 at 05:58 AM

    Thru MB51,You can find p.o no. from material document,In report,Click document list,Click change layout add purchase order no. field from hidden fields to left side,save layout.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 18, 2010 at 06:07 AM

    Hi

    If you know vendor number only then RUN ME2O by giving vendor number and it will display all PO nos for that vendor

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 18, 2010 at 06:19 AM

    Hi,

    In MB51, use movement type as 541, Enter vendor, Material ,plant ( any related information you know) enter posting date execute, in layout changes select Purchase Order field.

    Regards,

    Vikas

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 18, 2010 at 06:34 AM

    Hi,

    Previous answers were not correct - you cannot find the PO number in material document even if you execute the stock tranasfer to your subcontractor with reference to a PO in MB1B.

    E.g. if you delivered the compoenents already with reference to a PO you are able to use the same PO in MB1B to transfer the same components again (system suggests the.same components, same quantity).

    So, there's no such link between material movement and PO you are looking for.

    If you want to have reference you have to do it manually (e.g. as text remark) or go to development.

    Regards,

    Csaba

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 18, 2010 at 10:10 AM

    Hi,

    While doing 541 you can use the text field as your PO reference so that u can track the PO through material document.

    Regards,

    MBKM

    Add comment