Dear Experts,
I have created the project, network costing done, Budgeting done through CJ30, budget released through CJ32.
There is long lead materials attached to generate PR for preliminary requirement for advance procurement.
Now When I am trying to save the project after releasing, I am getting the error CO634.
When I checked the detailes in log it is showing the error
E BP 603
Item 010 WBS Elemnt XX.XX.XXXX budget exceeded.
Any idea what could be the reason..
There is commitment management activated from CO.
I have run CJBW and removed the availablity control, then this message is not coming.
Looking forward to hearing from you.
Thanking you.
Best Regards,
Abdul.