WE are developer company, so when a land is acquired we create the project under business development with nomenclature "BD/LG/01" with corporate profit centre linked to it (as we are not sure if the project takes of due to various issues.)

When the project commences we create another project structure with nomenclature "BE/LG/01u201D with new profit centre.

So when we transfer the cost lying in u201C BD u201D project to u201C BE u201C project by giving settlement profile, the cost get transferred using secondary cost element. when we see the statement through CJI3 report the cost would have get transferred but when we

see the report through Finance Profit Centre report the cost would have not transferred

So in order to get the report in profit centre, can we use primary cost element instead of secondary cost element, if we use the primary cost element what the consequence and what care needs to be taken for settlement.