on 12-10-2018 9:48 AM
All,
Client has a requirement that while confirmation COR6, Sloc should be picked for all components based on header material.
User fill Sloc in GR tab of process order for Header material and this same sloc should be picked for all components while COR6.
we cannot maintain it in Mat master as any prod can be manufactured in any of our plants.
Cannot maintain in BOM for similar reason ( our storage locs are manufacturing plants.)
Hello Akash,
You can maintain the Production supply area in the Work center/Resource. So that storage location will be picked based on the supply area.
Regards,
Prasath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
I the following thread I have explained the sequence used by the system to determine the components storage location:
https://archive.sap.com/discussions/thread/2125033
If none of these options are suitable for you, then you need to go for a custom development using a BAdI or exit to determine the storage location.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can update storage location in Production order.
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.