All,

Client has a requirement that while confirmation COR6, Sloc should be picked for all components based on header material.

User fill Sloc in GR tab of process order for Header material and this same sloc should be picked for all components while COR6.

we cannot maintain it in Mat master as any prod can be manufactured in any of our plants.

Cannot maintain in BOM for similar reason ( our storage locs are manufacturing plants.)

Accepted Solutions (0)

Answers (3)

Answers (3)

Prasath
Contributor
0 Kudos

Hello Akash,

You can maintain the Production supply area in the Work center/Resource. So that storage location will be picked based on the supply area.

Regards,

Prasath

former_member2091
Participant
0 Kudos

Hello Prasath,

Issue is we have work centers at plant level but client in SAP manufacturing locations are mapped as Slocs, so all manufacturing plants(Slocs) are using same work centers.

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

I the following thread I have explained the sequence used by the system to determine the components storage location:

https://archive.sap.com/discussions/thread/2125033

If none of these options are suitable for you, then you need to go for a custom development using a BAdI or exit to determine the storage location.

Regards,
Caetano

former_member2091
Participant
0 Kudos

Thanks for your revert Caetano.

We cannot fix Sloc on mat master or BOM or Work centers as they are also created at plant level and all Sloc(actual manufacturing sites) are using them.

Would you have any Badi or exit for this?

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Yes, there is an user-exit to change the storage location. This question has been asked several times in this space and you can find if you simple google it.

Amit_SAP
Active Contributor
0 Kudos

Hi,

You can update storage location in Production order.

Regards,

Amit