Stock Transport Request

Former Member
0 Kudos

Dear Experts,

1.I would like to create Stock Transport request through MRP run at the MRP Area level.Is it possible through Spl Pro Key?If not is there any means to generate?

2.Can I generate intercompany stock transport request through MRP run?If so,how?

Please guide me regarding this.

Regards

Reshmi

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Maintain SPK 40 in the Material master.

Mention the supllying plant as alternative plant

After MRP run STR will be created .

That can be converted into STO with the order type UB.

Vishal

Former Member
0 Kudos

Dear VS,

Thanks for the reply.What you suggested that is fine.But my problem is how can I create St Tr Req at the MRP area level,if my MRP Area Contains only Storage Location.Is there anything to configure Sp Pro Key against the MRP Area,not against the Plant?

Regards

Reshmi

Former Member
0 Kudos

Hi,

Yours requirement is not clear

You are executing MRP at MRP area and you want to procure material from another plant.

When you execute MRP it will create a PR having suplying plant(Another plant).

Now at other plant it will be having a demand though that PR/STO whenever MRP will be executed in another plant MRP element will

be created against PR/STO

Vishal