on 02-12-2010 5:58 AM
Dear Experts,
1.I would like to create Stock Transport request through MRP run at the MRP Area level.Is it possible through Spl Pro Key?If not is there any means to generate?
2.Can I generate intercompany stock transport request through MRP run?If so,how?
Please guide me regarding this.
Regards
Reshmi
Hi,
Maintain SPK 40 in the Material master.
Mention the supllying plant as alternative plant
After MRP run STR will be created .
That can be converted into STO with the order type UB.
Vishal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Yours requirement is not clear
You are executing MRP at MRP area and you want to procure material from another plant.
When you execute MRP it will create a PR having suplying plant(Another plant).
Now at other plant it will be having a demand though that PR/STO whenever MRP will be executed in another plant MRP element will
be created against PR/STO
Vishal