PP-PI: Selection of Process instruction categories

I created the control recipe destinations (CRD). The Process instruction categories were assigned in the CRD. I assigned the same CRD for two phases in the Master recipe. After executing the u2018create control recipesu2019 in the process order, then the following events happened :

1) Different process instruction categories are picked for phase 1 & 2 automatically and

2) Not all the process instruction categories are selected for each phase.

So, I would like to know what are the control parameters that influence the process instruction categories selection?

Regards.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Feb 11, 2010 at 07:34 AM

    Hi,

    For the control receipe destinations that you have generated check the Postitions / Sequence in the o10c,

    reg

    Dsk

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.