Skip to Content
0
Feb 10, 2010 at 05:50 PM

MII - Shift Level Reporting

122 Views

Hi MII Gurus,

What is the best and suggested method to handle shift information in MII? Can we configure MII to have the shift information? (example Shift: Work center1, 12 Hour Shift, this means there are 2 shifts for a given day). How long the shift level production information can be kept in MII? (short period reporting - for example: three months)

Do we really need to bring the production recipts with shift information to SAP?

For a given day SAP says production as 1000 Qty, but MII say 500 Qty was produced for the first shift and remaining was produced in second shift with exact production receipt time and details.

Is this a suggested process? It is my idea that we can avoid lot of shift level configs, shift level reporting and MII interfaces

with above approach.

Was any project impleted like this? Please share your ideas and thoughts.

Can we easily integrate MII with BI for the reporting?

Thanks

Nagarajan