Planned Delivery time not considered after MRP run for scheduling

Former Member
0 Kudos

Dear All,

After running MRP, the planned delivery time maintained in Purchase info record is not taken into consideration for calculating start date of the schedule line of externally procured material generated by the system.

Planned delivery time is 3 days & Requirement of parent material falls on 15/02/2010. With this, system should calculate the start date for schedule line as on 12/02/2010 considering 3 days Planned Delivery time.

Any idea as to what might have gone wrong?

thx for your help in advance.

Rgds,

Ranjeet

Accepted Solutions (0)

Answers (1)

Answers (1)

JL23
Active Contributor

Do you have a source list maintained where this vendor is marked as relevant for MRP ?

Only then MRP run will look into info records, without this MRP can only chekc the planned delivery time from material master

Former Member
0 Kudos

Hi,

We have already maintained Scheduling Agreement along with Source list with MRP relevancy -2.

Rgds,

Ranjeet

csaba_szommer
Active Contributor
0 Kudos

Hi,

Please check your settings for your plants / MRP group under:

SPRO > Production > MRP > Planning > Procurement Proposals > Define External Procurement

(Plant: V_399D_W-GTERM; mrp group: V_T438M_Q-GTERM)

One more question:

Did you maintain PDT in your scheduling agreement?

Regards,

Csaba

Former Member
0 Kudos

Hi,

Determination of PLD from the Purchase info record is maintained in transaction code:OMDT. Planned Delivery time is also maintained in Scheduling agreement. However, it is not calculating delivery date as well as release date.

Rgds,

Ranjeet

Former Member
0 Kudos

What is the release date you are getting now? Is it less or more? Have your consedered GR processing time and Purchase processing time(T.code OMEW). GR processing time and Purchase process time are workdays as per factory calender. System will consider this as well along with PDT to propose delivery date and release date

Regards

Antony

Former Member
0 Kudos

Hi,

PLD is maintained as 2 days. After running MRP, system should propose Release date 2 days prior to Requirement (Delivery) date for the schedule line generated.

GR processing time is not maintained as well as purchase processing time in OMEW.

Rgds,

Ranjeet

JL23
Active Contributor
0 Kudos

does your source list only have an entry for this vendor, or as well an entry for this schedule agreement?