Planned Delivery time not considered after MRP run for scheduling

590 Views

Dear All,

After running MRP, the planned delivery time maintained in Purchase info record is not taken into consideration for calculating start date of the schedule line of externally procured material generated by the system.

Planned delivery time is 3 days & Requirement of parent material falls on 15/02/2010. With this, system should calculate the start date for schedule line as on 12/02/2010 considering 3 days Planned Delivery time.

Any idea as to what might have gone wrong?

thx for your help in advance.

Rgds,

Ranjeet