Hi,

I am putting release procedure for PO, which takes release group 02. I have defined a new release strategy and new release codes( 3 levels). Now while doing release prerequisites, I have to give the combinations for code/release prerequisite.

My ques is how shd the marking to be done in the matrix of the three levels say P1, P2 & P3, so that no error of Release prerequisitions missing comes?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

at first all release codes are checked and the indicator is Blocked.

for ex: in oreder p1,p2,p3

no pre requite is required to releese at p1 level.

For p2 -


p1 should release first indicator is Blocked

For p3 -


p1 and p2 are to be released first indicator blocked

select the check for which prerequisite is needed.

Answers (1)

Answers (1)

Former Member
0 Kudos

hi

can you send the error screen shot