Hi Experts,
We have a situation where SAP PS WBS element captures planned cost but actual cost is not updated due to certain reason. Now we need to update actual cost directly in WBS element. E.g. 1000 USD as Planned cost and need to update actual cost as 1000 USD in WBS. Could anyone please help how to capture or post actual cost directly in WBS and how many ways we can achieve this with Tcodes.
Regards,
Dileep
The financial transaction allows you to book cost or revenue to the WBS directly.
KB21N --> Used to post Activity type i.e. booking cost using cost center/activity type similar to activity confirmation with personal number . (business transaction RKL)
KB15N --> Used to post against the CE for WBS using cost center. Business Transaction - COIN similar to of material posting
KB11N --> Used for cost reposting to CE by transferring the cost from one WBS to Other WBS or cost center to WBS so on. Business Transaction - COIN - might be...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Actual costs are posted to the WBS through many different transactions. Time charging, Purchase Orders, Material Issues, Asset Depreciation, Direct FI postings, etc. etc. What do you mean when you say you need to update the actual costs?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dileep,
You can post actual cost to WBS using t-codes: KB11N, KB21N, KB15N
based on your requirement you can use any of this t-code
Thanks
Praveen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.