How to post actual cost in WBS element directly.

dileepkurupk
Explorer
0 Kudos

Hi Experts,

We have a situation where SAP PS WBS element captures planned cost but actual cost is not updated due to certain reason. Now we need to update actual cost directly in WBS element. E.g. 1000 USD as Planned cost and need to update actual cost as 1000 USD in WBS. Could anyone please help how to capture or post actual cost directly in WBS and how many ways we can achieve this with Tcodes.

Regards,

Dileep

ajitkumar
Active Contributor
0 Kudos

Has the cost come to the system but to a different cost object ( like Cost center, internal order etc )

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member469721
Participant
0 Kudos

The financial transaction allows you to book cost or revenue to the WBS directly.

KB21N --> Used to post Activity type i.e. booking cost using cost center/activity type similar to activity confirmation with personal number . (business transaction RKL)

KB15N --> Used to post against the CE for WBS using cost center. Business Transaction - COIN similar to of material posting

KB11N --> Used for cost reposting to CE by transferring the cost from one WBS to Other WBS or cost center to WBS so on. Business Transaction - COIN - might be...

kenmelching
Active Contributor
0 Kudos

Actual costs are posted to the WBS through many different transactions. Time charging, Purchase Orders, Material Issues, Asset Depreciation, Direct FI postings, etc. etc. What do you mean when you say you need to update the actual costs?

praveen_vanm
Participant
0 Kudos

Hi Dileep,

You can post actual cost to WBS using t-codes: KB11N, KB21N, KB15N

based on your requirement you can use any of this t-code

Thanks

Praveen